PROJECT

Project Information & Monitoring Update

19 Aug 2020 ELECTRICITY SECTOR

Dieng Unit 2 Geothermal Power Plant (PLTP) Development Project and Patuha Unit 2 PLTP

GeoDipa has successfully completed financing efforts for the construction of the Dieng Unit 2 Geothermal Power Plant (PLTP) and the Patuha Unit 2 PLTP with a capacity of 55 MW each. This effort has the full support of the Ministry of Finance and PT Penjaminan Infrastruktur Indonesia (Persero) / PT PII, which is also the Ministry of Finance's SMV, which is mandated to provide government guarantee facilities for the development of the power plant project.

Project Information

Location Dieng & Patuha
Project Value IDR 6,9 Trillion
Lenders Asian Development Bank (ADB)
Guaranteed Debtor PT Geo Dipa Energy

PT PII and GeoDipa today, Wednesday (19/08) signed an agreement with the Asian Development Bank (ADB) for the Dieng Unit 2 Geothermal Power Plant (PLTP) Development Project and Patuha Unit 2 PLTP, as part of the efforts to provide electricity through the utilization of geothermal New Renewable Energy (EBT). The signing of the project includes the signing of a loan agreement between GeoDipa and ADB, the signing of the Guarantee Agreement between the Ministry of Finance and ADB, and the signing of the Guarantee Implementation Agreement between PT PII and GeoDipa. 

BACK TO PROJECT